    I was wondering if it was ok to continue laying blocks for my wall in light rainy conditions or if this would be dtrimental to the finished wall.

    Intermittent showers are forcast all weekend with us so if i could lay some blocks and then stop during the rainy spells and cover work and mortar with plastic sheet would this be ok?

    Also how long would it take for te mortar to be unworkable?

    thanks
    Trevor
     
  2. ^woody^

    Joined:
    3 Sep 2006
    Messages:
    13,522
    Thanks Received:
    1,357
    Location:
    Birmingham
    Country:
    United Kingdom
    The rain is not the probelm.

    The issue is whether the rain washes out the mortar and stains the wall. And the increased likeliness of efflorescence from saturated bricks

    Cover the wall, the stacks of unlaid bricks, and the unused mortar.

    Mortar is useable for anything upto 3/4 hour
     
  3. Shytalkz

    Joined:
    22 Feb 2008
    Messages:
    4,864
    Thanks Received:
    13
    Location:
    Norfolk
    Country:
    United Kingdom
    I'm just sitting laying brickwork in the rain,
    feel the power of the rain,
    making the garden grow..
     
  4. chessspy

    Joined:
    23 Apr 2008
    Messages:
    483
    Thanks Received:
    2
    Location:
    Kent
    Country:
    United Kingdom
    The Bretheren say,
    The drystone wall that surrounds the universe requires no mortar.
    No architect of confusion is needed by the bretheren of the wall.
    Honest sons of toil should join the bootherhood.







    Not so much a religion, more a bunch of cults.
     
  5. tflda29

    Joined:
    3 May 2006
    Messages:
    67
    Thanks Received:
    0
    Location:
    Aberdeenshire
    Country:
    United Kingdom
    the wall is only a block retaining wall which will eventually be covered so not bothered about staining. as long as all the mortar does not get washed out!
     
  6. chessspy

    Joined:
    23 Apr 2008
    Messages:
    483
    Thanks Received:
    2
    Location:
    Kent
    Country:
    United Kingdom
    Goferit
     
  7. noseall

    Joined:
    2 Feb 2006
    Messages:
    21,431
    Thanks Received:
    1,349
    Location:
    Staffordshire
    Country:
    United Kingdom
    masonry actually benefits from being laid wet. it will be stronger, albeit messier. :eek: ;)
     
  8. joe-90

    Joined:
    28 Oct 2005
    Messages:
    30,164
    Thanks Received:
    928
    Country:
    United Kingdom
    The old time brickies used to soak their bricks so the mortar cured before it dried out.
     
  9. noseall

    Joined:
    2 Feb 2006
    Messages:
    21,431
    Thanks Received:
    1,349
    Location:
    Staffordshire
    Country:
    United Kingdom
    they still do! :LOL:
     
  10. NS215

    Joined:
    1 Aug 2006
    Messages:
    490
    Thanks Received:
    4
    Location:
    Cheshire
    Country:
    United Kingdom
    .


    Mortar is useable for anything upto 3/4 hour[/quote]

    unless of course its ready mix with a retarder in it then upto 72 hrs :LOL:
     
  11. tflda29

    Joined:
    3 May 2006
    Messages:
    67
    Thanks Received:
    0
    Location:
    Aberdeenshire
    Country:
    United Kingdom
    thanks for replies all....i finally managed to get the first course laid yesterday and covered before the rain came on again...
     
  12. ^woody^

    Joined:
    3 Sep 2006
    Messages:
    13,522
    Thanks Received:
    1,357
    Location:
    Birmingham
    Country:
    United Kingdom
    Bad weekend for laying bricks here too .... the sun was just too hot for the back :evil:
     

Share This Page