Won't bore you with details of the job( a raft 18ft by 12ft by 4") but if I got the materials(32 bags cement, 3T sand and 3T of 20mm gravel) how long would it take realistically to do 2m cubed just myself(fairly fit and strong enough...), and what size of mixer would speed up the process significantly(bigger than a 1/2 bag belle jobbie....)
A day or would I need 2 days and chuck in some retarder?
A day or would I need 2 days and chuck in some retarder?