Start date for different elements

Joined
18 Jun 2009
Messages
79
Reaction score
1
Location
Tyne and Wear
Country
United Kingdom
Hello all, i'm sure this has been covered before but i am struggling to lay my hands on it. My client would like a front proch (requires planning) and a side extension (also requires planning), she is not sure whether they will be both done at the same time due to budget. My question is... if she starts (and finishes) the porch within three years af approval, can she claim the planning permission remains active until she decides to do the side? Or is each element required to be started before the expiration of three years?

Thanks

Eddy
 
Sponsored Links
The permission is enacted once any part of the work is [significantly] started

So, if 10 things were on the same application/permission, then once one is started then that enacts the permission for the other nine
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top