Hi there,

I have Planning Approval for a small stable block. I have poured the concrete base, but job uncertainty means that I'd prefer to delay building the superstructure for a while, potentially years. The stables do not require Blg. Regs. approval.

When does my Planning Approval expire now that I have commenced the build?

Thanks
 
Sponsored Links
Thanks.

The only Conditions are that the development begins within 3 years and it is built in accordance with the plans.

I take it that pouring the fonudation slab constitutes commencement.

I guess I can leave it for a while then.

Thanks for taking the time to answer my question.
 
Sponsored Links
Yes it does. Assuming you have submitted a Building Regulation application, call out an inspector (if you haven't done so already) so they can note the works have commenced "just incase" you leave it for a looong time and then planning ask you (e.g.) in three years to prove the slab was done within the three years of the decision date.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top