  1. paulandfrodo replied to the thread How long fire protection around internal steel RSJ.

    Got the reply from BC. I'll put some intumescent on the joins and he's asked we put the skim on to 5mm rather than 3mm. Seeing the he...

    27 May 2020 at 2:00 PM
  2. paulandfrodo replied to the thread How long fire protection around internal steel RSJ.

    Thanks woody, I've approached the inspector with suggested solutions. I've also said that if I have to, I will just crack on and double...

    27 May 2020 at 12:36 PM
  3. paulandfrodo attached a file to the thread How long fire protection around internal steel RSJ.

    Hey woody. I normally use an independent inspector, however this time I've used a local one. Historically I have always done 12.5mm...

    d20ad82c-f71e-4cc3-ba35-41e39aa175a9.jpeg IMG_6018.jpeg IMG_6019.jpeg 27 May 2020 at 11:39 AM
  4. paulandfrodo replied to the thread How long fire protection around internal steel RSJ.

    If it's 60 mins, then you are right, the white paper shows 15mm thickness. I just was not sure if it was 60 or 30 mins. I can still do...

    27 May 2020 at 10:15 AM
  5. paulandfrodo posted a new thread.

    How long fire protection around internal steel RSJ

    I have had a look in Part B Volume 1 and cannot see the answer, it could be that I'm in a fuss and not looking hard enough. I have...

    Forum: Building Regulations and Planning Permission