Hi
Appreciate this has been covered before so I apologise that I can't quite figure it out in my case
I am digging about 30m of foundations to trench fill, and I was planning on chuting it straight in off the truck and working it to flow around and fill everything (working on my own or with 1 guy, my dad)
However half way round is 2 drains running low down across the trench (600mm ish) and it's just struck me that my plan of shuttering them off completely, ( as advised by bco) will mean I've got no way of pouring the "other side", as there's no access from the front / for the truck. I think if I try to barrow that amount I'm asking for trouble!
Wrapping in compressible material sounds good to me but I think the pipes are too low?
I guess one option is 2 separate pours, covering over the pipes after the first pour has set?
Sorry guys I know this has been asked before but any advice appreciated. If it was a smaller size it would be less of an issue.
Cheers
John
Appreciate this has been covered before so I apologise that I can't quite figure it out in my case
I am digging about 30m of foundations to trench fill, and I was planning on chuting it straight in off the truck and working it to flow around and fill everything (working on my own or with 1 guy, my dad)
However half way round is 2 drains running low down across the trench (600mm ish) and it's just struck me that my plan of shuttering them off completely, ( as advised by bco) will mean I've got no way of pouring the "other side", as there's no access from the front / for the truck. I think if I try to barrow that amount I'm asking for trouble!
Wrapping in compressible material sounds good to me but I think the pipes are too low?
I guess one option is 2 separate pours, covering over the pipes after the first pour has set?
Sorry guys I know this has been asked before but any advice appreciated. If it was a smaller size it would be less of an issue.
Cheers
John