Hi guys

I have to make up levels prior to tiling and after UFH cement boards are laid. This is so the finished floor level is flush with the sliding door aluminium frame.

After the UFH boards 18mm I have 35mm to get a flush level. The tile is 11mm, 3mm DITRA and 6mm adhesive leaves me with 15mm.

If I use self levelling compound this will be the best option but a lot
Of work. Could I use plywood or even Celotex type board?

Any suggestions welcomed!

Thanks
Mikeinthemidlands
 
Sponsored Links
why not use the search button to look for "ufh"?

i dont want to get involved with trying to answer your question but fwiw will raising the FFL to meet the alu frame cause any knock-on problems with adjoining room threshold levels?
 
How about under the UFH boards fix some 12mm backer Boards first. Trowel out some flexi adhesive under the boards, then screw down, and you have 15mm.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top