Hi me again With a Few questions (the pain in the arse)
1.if the planning goes ahead for the double story extension would I need to get a build over agreement being the last serving property on the line
2.there is going to be a manhole in my extension that i would like to remove as al I can think it’s for is rodding access as it has a straight channel inside
from what Information I can find online I’m the private owner off the drains being the last serving property
my plans are to dig the drain out and change to plastic at the boundary as it’s only around 650mm deep stick a junction on the line going to a small inspection chamber. Then where the manhole pics up my internal soil stack replace this with a junction. Hopefully stick 45degree bend on the end to form rodding eye.
I’m then hoping to run aco drains along my building At dpc as her in doors wants there to Be no 150mm step down with the kids.
so basically am hoping to connect the acos to the small inspection chamber with a trapped connection And run both my downspouts from my extension and kitchen waist into them being combined or if possible get rid the inspection chamber just have the connection for the acos
I can only apologise for my poor grammar and spelling and poor drawings here’s existing and what am thinking
1.if the planning goes ahead for the double story extension would I need to get a build over agreement being the last serving property on the line
2.there is going to be a manhole in my extension that i would like to remove as al I can think it’s for is rodding access as it has a straight channel inside
from what Information I can find online I’m the private owner off the drains being the last serving property
my plans are to dig the drain out and change to plastic at the boundary as it’s only around 650mm deep stick a junction on the line going to a small inspection chamber. Then where the manhole pics up my internal soil stack replace this with a junction. Hopefully stick 45degree bend on the end to form rodding eye.
I’m then hoping to run aco drains along my building At dpc as her in doors wants there to Be no 150mm step down with the kids.
so basically am hoping to connect the acos to the small inspection chamber with a trapped connection And run both my downspouts from my extension and kitchen waist into them being combined or if possible get rid the inspection chamber just have the connection for the acos
I can only apologise for my poor grammar and spelling and poor drawings here’s existing and what am thinking