Looking to get foundations dug for an extension. 1.2m deep, 18m long (in total) and 600mm wide. Soil is sand and clay. No rocks.

Struggling to get a hold of people at the moment (industry seems to be booming), but have managed to get 1 guy over.

I had initially expected it to be a 2 day job, but he surprised me by saying it would take at least 5 days for 2 people. 1 on digger, 1 on dumper. Just curious whether I got this all backwards.

There is reasonable access for a digger and 1 ton dumper.
 
Sponsored Links
Where is the excavated soil intended to be dumped? and what distance from the dig site?

Ken.
 
Sponsored Links
As "woody" above.

if these guys are on a rate per hour as opposed to a firmly agreed fixed cost then ???

Your original 2 days will more than cover this extent of work.

Ken
 
Thanks. Will have another chat with him. I'm trying to save cost by splitting the work up and getting people in to do parts of the build, and doing parts myself. Even if I have to pay him for a week it'll still work out a lot cheaper than the initial quote I got from a company that would manage and complete the build in house. Sounds like it's either that, or wait for someone else to become available and they're all booked until November by the sound of it.
 
Understood, welcome to the world of Project Management?

If nothing else you can add that title to your CV???
 
Looking to get foundations dug for an extension. 1.2m deep, 18m long (in total) and 600mm wide. Soil is sand and clay. No rocks.

Struggling to get a hold of people at the moment (industry seems to be booming), but have managed to get 1 guy over.

I had initially expected it to be a 2 day job, but he surprised me by saying it would take at least 5 days for 2 people. 1 on digger, 1 on dumper. Just curious whether I got this all backwards.

There is reasonable access for a digger and 1 ton dumper.

If its any guide it took me 2 days to dig 1.2m deep, 500mm wide 6m total length by hand, by myself. Horrible ballast, flint ridden sandy soil you couldn't get a shovel into
 
It is. Thanks! Did consider that as I don't mind digging, but with it being 3 times what you had to do I think I would've struggled doing it for 6 days. Especially as I typically sit behind a desk all day.
 
To be fair my total amount dug was about 14m total but the extra was done over a couple of weeks between work commitments.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top