Simple question:
I am installing a new ring final circuit (LABC notified). Rather that have the building inspector poo-poo my work, thought I had better check I was doing it right.
At two points in the circuit, a cable goes from one side on the lounge to the other via the ceiling. It runs in parallel with the joists. I installed it by lifting a floor board at each side of the room above and poking the cable across with a long rod. The cable is therefore not therefore supported along this length (approx. 3m) except by the plasterboard ceiling. Is this OK? If not what is the suggested way to deal with it? I have no loose floorboards in the middle of the cable run.
I know that where cables pass though joists they need to go via a hole in the middle. If I have the situation where there are a few cables in a hole and it would be tight to get another it, will I get picked up on that?
I am installing a new ring final circuit (LABC notified). Rather that have the building inspector poo-poo my work, thought I had better check I was doing it right.
At two points in the circuit, a cable goes from one side on the lounge to the other via the ceiling. It runs in parallel with the joists. I installed it by lifting a floor board at each side of the room above and poking the cable across with a long rod. The cable is therefore not therefore supported along this length (approx. 3m) except by the plasterboard ceiling. Is this OK? If not what is the suggested way to deal with it? I have no loose floorboards in the middle of the cable run.
I know that where cables pass though joists they need to go via a hole in the middle. If I have the situation where there are a few cables in a hole and it would be tight to get another it, will I get picked up on that?