Hi there,
A couple of quick questions - any comments/advice would be greatly appreciated.
I'm currently digging my foundations to save as much money as possible before getting builders in to do the brickwork etc. and have a couple of questions...
The details below are what I have found researching online, I am a DIYer so I am not a professional - please critic/make comments/ recommendations
1) Sewer pipe through foundations:
There is to be a new sewer pipe going through the foundations, looking online is it correct to just leave a gap in the foundation concrete (pipe width to the bottom of trench), and then use 2x concrete lintel for each wall leaf above? (to support single story extension) ...either side wont move as they are not joined...?
Example I found online:
It's ok to leave a full gap to the bottom of trench for the pipe work? :/
2) Is it ok to fill trench fill concrete in stages.. i.e. do a small section at a time wait for it to set, then do next section several days later?
I watched a video where the builder filled their trench with concrete in stages, left it to dry then did the next bit over a few days- I would have thought if you did it this way to have rebar rods in the end joining the set concrete to the new bit you are laying for strength?
I was under the impression the whole length of trench would have to be laid same day?
Example - in the video the strip joining the house has just been poured, the rest is already dry from day or two previous..
A couple of quick questions - any comments/advice would be greatly appreciated.
I'm currently digging my foundations to save as much money as possible before getting builders in to do the brickwork etc. and have a couple of questions...
The details below are what I have found researching online, I am a DIYer so I am not a professional - please critic/make comments/ recommendations
1) Sewer pipe through foundations:
There is to be a new sewer pipe going through the foundations, looking online is it correct to just leave a gap in the foundation concrete (pipe width to the bottom of trench), and then use 2x concrete lintel for each wall leaf above? (to support single story extension) ...either side wont move as they are not joined...?
Example I found online:

It's ok to leave a full gap to the bottom of trench for the pipe work? :/
2) Is it ok to fill trench fill concrete in stages.. i.e. do a small section at a time wait for it to set, then do next section several days later?
I watched a video where the builder filled their trench with concrete in stages, left it to dry then did the next bit over a few days- I would have thought if you did it this way to have rebar rods in the end joining the set concrete to the new bit you are laying for strength?
I was under the impression the whole length of trench would have to be laid same day?
Example - in the video the strip joining the house has just been poured, the rest is already dry from day or two previous..
