Hi,
I have one proper slab - 150mm w. steel mesh, then some sand blinding, then the DPM, then 100mm of celotex. I then should have poured the remaining 130mm upto FFL, but i didn't - don't ask me why! I am now 50mm short of FFL.
I suppose all i would like to know, is not whether a screed is...