guess best route is to work with a qualified spark. I can run in cables etc where he tells me and he can do connecting and certifying
Had electrician connect up the new house consumer unit. Was just a bit concerned because when I called him to explain change of plan to having one supply for...
Building Regs were passed a month ago. Part P does apply and am opting to do it myself and get an electriction to certify it ( :? if I can do that !! )
Original plan was for two separate 6mm feeds from house CU. One to supply greenhouse electric/heater and one to garage. This was planned...
Brilliant..much appreciated.
So plan is to use BOTH 6mm T&E cables run together from same MCB already available at house consumer unit to connect to one 10mm 3 core SWA to run underground and supply garage CU 5m away
This supply to garage CU should then be sufficient for requirements now...
Having an extension done now and need to put an armoured cable feed to garage now before floors concreted
I have two spare 6mm twin and earth cables routed from the consumer unit (but not connetced to supply) sitting in ceiling space ready to be connected to anything. Put these in before...