Well builders came today and weren't at all happy about me involving council BI as the said they would put it right. Cue a heated exchange of words while waiting the BI came out. Including builder threatening to rip out the work he had done there and then if I was that unhappy about it!
BI...
Thank you theoldun. I have had a reply from the BI this lunchtime. He is coming out tomorrow to meet with the builder to take a closer look at the work and state what needs doing to rectify it.
I plan to ask the builder to put in writing the work he is going to carry out before he starts...
Cheers for that Tony. I'll give BI some time to respond then look at a surveyor. Is there anything specific I should be asking the surveyor? It may be a silly question but this is all getting out of my comfort zone now and want to make sure I am paying for the right service.
Thanks
Hi Andy
I have emailed building control with my concerns and included photos and have requested that the roof is resurveyed to find all issues. Waiting now for a reply.
That's the problem. This is a roof on a newly built extension. Building control had checked it throughout the build and issued the completion certificate last week!
Have contacted them in the first instance to explain how this was missed / was passed.
Here are some more images. as requested.
Please offer some advice. After 17 weeks for a build i was told would take 8 the stress of all the problems has taken its toll and I'm at a lose at what to do for the best.
Hi hope this is the correct place to post this. I have had a single extension built. It is almost finished in-spite of numerous issues that I wont go into now. I have noticed issues with the roof, mainly with the quality of the lead flashing. My builder has agreed there is an issue, and is...