Hi,
I'm replacing a the control part of an electric heating system which uses 2 of 3 60a phases in a commercial building. Theres 10 electric heaters - 5 on each phase.
I want to use a 4pole wylex contactor (switched with a programmer) for the 2 supplies, which will turn on the two CU's.
I'm seeking abit a clarity on how I can use the contactor. I was going the place the the supply inputs as follows Neutral - T1, Phase 1 - T3, Phase 2 - T5
Outputs to CU's - Neutrals to both CU's - T2, CU1 Live - T4, CU2 Live - T6.
Is the right or am i mistaken?
Cheers
I'm replacing a the control part of an electric heating system which uses 2 of 3 60a phases in a commercial building. Theres 10 electric heaters - 5 on each phase.
I want to use a 4pole wylex contactor (switched with a programmer) for the 2 supplies, which will turn on the two CU's.
I'm seeking abit a clarity on how I can use the contactor. I was going the place the the supply inputs as follows Neutral - T1, Phase 1 - T3, Phase 2 - T5
Outputs to CU's - Neutrals to both CU's - T2, CU1 Live - T4, CU2 Live - T6.
Is the right or am i mistaken?
Cheers