Hi,
I'm busy thinking over an extension for the rear of the house and reviewing a number of challenges which would need to be overcome.
The main issue is that there is very little access to the rear of the property, let alone sufficient to swing an 8m steel to keep up the rear of the first floor in order to open up the rear.
The question therefore is, I know it's possible to splice a connection, however is it feasible to splice into 3 sections, this making it easier to get into position and maneuver?
Thanks.
I'm busy thinking over an extension for the rear of the house and reviewing a number of challenges which would need to be overcome.
The main issue is that there is very little access to the rear of the property, let alone sufficient to swing an 8m steel to keep up the rear of the first floor in order to open up the rear.
The question therefore is, I know it's possible to splice a connection, however is it feasible to splice into 3 sections, this making it easier to get into position and maneuver?
Thanks.