Hi chaps,
For my thickened raft, under the slab I need to put some Hoggin.
Q. If I was to Blind the Hoggin with sand, what type of sand and what exactly do I have to do?
Q I can work out the volume of Hoggin that I require, but the delivery is in weight. Any ideas what the equation rate is?
Somebody suggested 2Tonne = 1M3?
Cheers,
James.