Hi All
I’m after some advice if possible,
We are just starting to build a small extension and have an issue relating to ground levels on one side of the proposed extension because next doors drive slopes upwards which means the ground there is 3-4 courses higher than the internal floor level and the existing DPC level of the property.
We proposed to install the DPM from the base into the DPC as normal on the internal wall and on the inside of the external wall wrap DPM from the base of the first course of bricks up the inside and then link to DPC 150mm above the outside ground level and install a cavity tray from two courses above internally to a weep hole above the DPM externally.
We also wondered if it would be Appropriate to somehow prevent moisture rising from under the base of the internal leaf? How could we do this?
We have submitted our plan to building control and the inspector says we can’t use DPM to effectively ‘tank’ a vertical wall. He hasn’t yet offered an alternative and is now unavailable for several days which isn’t ideal as our builder is set to start laying bricks.
How can we easily resolve this?
Can anyone offer any advice or share experiences of a similar situation.
Thanks in advance
Lisa
I’m after some advice if possible,
We are just starting to build a small extension and have an issue relating to ground levels on one side of the proposed extension because next doors drive slopes upwards which means the ground there is 3-4 courses higher than the internal floor level and the existing DPC level of the property.
We proposed to install the DPM from the base into the DPC as normal on the internal wall and on the inside of the external wall wrap DPM from the base of the first course of bricks up the inside and then link to DPC 150mm above the outside ground level and install a cavity tray from two courses above internally to a weep hole above the DPM externally.
We also wondered if it would be Appropriate to somehow prevent moisture rising from under the base of the internal leaf? How could we do this?
We have submitted our plan to building control and the inspector says we can’t use DPM to effectively ‘tank’ a vertical wall. He hasn’t yet offered an alternative and is now unavailable for several days which isn’t ideal as our builder is set to start laying bricks.
How can we easily resolve this?
Can anyone offer any advice or share experiences of a similar situation.
Thanks in advance
Lisa