Looking to get foundations dug for an extension. 1.2m deep, 18m long (in total) and 600mm wide. Soil is sand and clay. No rocks.
Struggling to get a hold of people at the moment (industry seems to be booming), but have managed to get 1 guy over.
I had initially expected it to be a 2 day job, but he surprised me by saying it would take at least 5 days for 2 people. 1 on digger, 1 on dumper. Just curious whether I got this all backwards.
There is reasonable access for a digger and 1 ton dumper.