I have a new build granted and if I don't start the work up to the 3yrs period, is it a case of rubber stamp it again or have I got to reapply the full application again or is it so they can add any latest regulations?
There is a specific kind of application for "renewal of an extant permission" that may apply to your situation, and attracts a lower fee:
http://www.planningportal.gov.uk/uploads/1app/guidance/guidance_note-extensions.pdf[/QUOTE]
Bear in mind...
"It is not possible to use this procedure where the permission or consent has already expired at the time of application, or where the permission/consent was granted after 1 October 2010. In such cases, a new application would have to be made."
You only actually need to dig a single hole in the right place,
You only actually need to dig a single hole in the right place,
I doubt digging a hole would constitute a 'start' for the purposes of the Act, it would need something far more substantial - excavating and pouring concrete footings would be start - also laying drainage for the approved building, for example.
If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.
Select the supplier or trade you require, enter your location to begin your search.
Are you a trade or supplier? You can create your listing free at DIYnot Local