Hi all,
You are always the font of all knowledge, so thank you in advance.
We have a non "competent person" registered builder installing an en suite. I mean non-competent person as in not registered under the scheme, but I have full confidence in his competency though. If that makes sense?
Am I right in thinking that our works are non-notifiable as :
1) There are no new circuits being installed, he has used existing circuits.
2) There are no electrics within 2.25m from the floor level above the shower head / to the shower head height (if higher than 2.25m) and within 60cm direction outwards.
3) There is a spotlight above the shower tray (but this is more than 2.25m from floor level and above shower head height) and is one of these which is IP65 (https://www.screwfix.com/p/lap-fixed-led-downlight-370lm-white-4w-220-240v/3046v)
4) There will be a fused spur and a digital mixer unit for the shower controls but these will be in the loft OR in the cupboard of the room next to the bathroom, i.e. cabling through the wall and isolated from a dry area.
I'd really appreciate your comments, I fully trust our builder but also just want clarification that what I have understood from him is correct.
Thanks all
You are always the font of all knowledge, so thank you in advance.
We have a non "competent person" registered builder installing an en suite. I mean non-competent person as in not registered under the scheme, but I have full confidence in his competency though. If that makes sense?
Am I right in thinking that our works are non-notifiable as :
1) There are no new circuits being installed, he has used existing circuits.
2) There are no electrics within 2.25m from the floor level above the shower head / to the shower head height (if higher than 2.25m) and within 60cm direction outwards.
3) There is a spotlight above the shower tray (but this is more than 2.25m from floor level and above shower head height) and is one of these which is IP65 (https://www.screwfix.com/p/lap-fixed-led-downlight-370lm-white-4w-220-240v/3046v)
4) There will be a fused spur and a digital mixer unit for the shower controls but these will be in the loft OR in the cupboard of the room next to the bathroom, i.e. cabling through the wall and isolated from a dry area.
I'd really appreciate your comments, I fully trust our builder but also just want clarification that what I have understood from him is correct.
Thanks all