I have bathroom ripped out and want some comments on this quote.
I asked a plumber to give me a quote for following:
1. Close 8mm microbore radiator pipes as not working.
2. Install new radiator of the oil central heating system, towel rail.
3. Redirect sink pipes and waste up the wall.
4. Redirect toilet pipes 1 foot to another wall.
5. Fit new shower tray with waste and seals and supply water for electric shower for tiling.
6. Fit bath with seals.
I have all materials except pipe work and I advised I can track walls and floor necessary.
I was given a quote of £700 first fix and £700 second fix
I have bathroom ripped out and want some comments on this quote.
I asked a plumber to give me a quote for following:
1. Close 8mm microbore radiator pipes as not working.
2. Install new radiator of the oil central heating system, towel rail.
3. Redirect sink pipes and waste up the wall.
4. Redirect toilet pipes 1 foot to another wall.
5. Fit new shower tray with waste and seals and supply water for electric shower for tiling.
6. Fit bath with seals.
I have all materials except pipe work and I advised I can track walls and floor necessary.
I was given a quote of £700 first fix and £700 second fix