Hi,
Newbie here.
We have planning permission granted for a two storey rear extension and single side extension to our three-bed semi. The permission expires December 2013.
Can I start digging the foundations for the side extension, get them approved by the building inspectorate, and, assuming we would not actually build the extension (due to 2nd baby arriving in December 2012) until after the permission expiry date comes about (Dec 2013), do I need to go back to apply for planning permission for the actual building?
Sorry if this is a bit of a dis-jointed question.
Regards, Rich.
Newbie here.
We have planning permission granted for a two storey rear extension and single side extension to our three-bed semi. The permission expires December 2013.
Can I start digging the foundations for the side extension, get them approved by the building inspectorate, and, assuming we would not actually build the extension (due to 2nd baby arriving in December 2012) until after the permission expiry date comes about (Dec 2013), do I need to go back to apply for planning permission for the actual building?
Sorry if this is a bit of a dis-jointed question.
Regards, Rich.