ok... the scenario
i need to run an swa from a new meter supply (which has yet to be installed) up to a flat 45mts away. i cant calculate the size yet for obvious reasons.

the flat currently has a 6w board for power & lighting and a seperate board for storage heaters.

as this is an swa, i obviously cant just split the supply using henly blocks and so, in your opinion, what would be the best method to use in this situation?
 
Sponsored Links
Sponsored Links
yup, good call, i was thinking along these lines but its always best to have a 2nd opinion just in case :mrgreen:
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top