    Surely scaffolding planks should be secured?

    My neighbour is having Solar panels fitted and one of the scaffolding planks at 1st floor level has just slide off and smashed into my bay window tiles!

    Two tiles on the end of the ridge smashed and of course it started to rain straight away!

    made a temporary fix to stop the influx of rain!

    My neighbour got onto the company straight away and the guy has come out and will get his roofer to come out tomorrow and either fix it or on Monday if no tiles in stock.

    But surely this should not happen, it could have been much worse?

    How should planks be secured?
     
  2. ^woody^

    Joined:
    3 Sep 2006
    Messages:
    13,769
    Thanks Received:
    1,394
    Location:
    Birmingham
    Country:
    United Kingdom
    Traditional scaffold boards are not normally secured, and don't jst slide off

    If its a tower or suchlike with lightweight aluminium staging, then these normally have anti-lift clips
     
  3. catlad

    Joined:
    29 Jul 2011
    Messages:
    2,217
    Thanks Received:
    325
    Location:
    Lancashire
    Country:
    United Kingdom
    The boards blew of a job I was doing about a month ago 12' planks lucky they landed in the field 25 yds away. yes they should be fixed down but frequently not.
     
  4. ladylola

    Joined:
    19 Dec 2009
    Messages:
    3,041
    Thanks Received:
    260
    Location:
    Staffordshire
    Country:
    United Kingdom
    Woody's right planks aren't normally secured but in exposed conditions or around a particulary vunerable building they sometimes are.
    There are a number of ways to do it, the simplist is to tie each plank down with a single clip . I don't mean single as in just one clip per board I'm refering to what are sometimes called putlog clips and normally two are used per board at least. An alternative is to clamp a scaffold pole across the top of the boards which in itsself creates a wonderful tripping hazard and I've also seen planks lashed down with rope.
    Still the good thing is the company responsible have acted quickly.
     
  5. datarebal

    Joined:
    1 May 2007
    Messages:
    993
    Thanks Received:
    105
    Location:
    Hampshire
    Country:
    United Kingdom
    there are specific clips for boards.... not many company use them and if they do only on short boards or in exposed places...
     
  6. ladylola

    Joined:
    19 Dec 2009
    Messages:
    3,041
    Thanks Received:
    260
    Location:
    Staffordshire
    Country:
    United Kingdom
    I'd forgot about them, it's been so long since I've seen one used :LOL:
     
  7. Xenon

    Joined:
    10 May 2008
    Messages:
    594
    Thanks Received:
    69
    Location:
    Essex
    Country:
    United Kingdom
    We won't take handover of a scaffold unless boards are strapped/clipped. Domestic applications included.
     
  8. Roton600

    Joined:
    9 Aug 2011
    Messages:
    49
    Thanks Received:
    3
    Location:
    Hampshire
    Country:
    United Kingdom
    The roofing guy has just been out and will be sorting out the tiles Monday, so that,s good.

    The next question:
    Should i be making a complaint to the Solar panel installer company, who have obviously subcontracted the scaffolding to a local company telling them of the problem, or anyone else as although it is getting fixed, it could have been a lot worse.

    http://www.diynot.com/network/Roton600/albums/
     
  9. ladylola

    Joined:
    19 Dec 2009
    Messages:
    3,041
    Thanks Received:
    260
    Location:
    Staffordshire
    Country:
    United Kingdom
    I don't know about a complaint seeing as the scaffold company have accepted they are to blame and are acting quickly and in good faith to solve the problem , so everything in this case is amicable. However, it may be worth informing the solar company of what has happened , they may then revise future orders for scaffold.
     
  10. ^woody^

    Joined:
    3 Sep 2006
    Messages:
    13,769
    Thanks Received:
    1,394
    Location:
    Birmingham
    Country:
    United Kingdom
  11. noseall

    Joined:
    2 Feb 2006
    Messages:
    21,605
    Thanks Received:
    1,373
    Location:
    Staffordshire
    Country:
    United Kingdom
    My thoughts too. From the language i was expecting at least a modest amount of damage.

    I would be more upset by the lack of head-lap on those tiles and thank the scaffolding company for exposing poor workmanship.
     
    • Thanks Thanks x 1
  12. ^woody^

    Joined:
    3 Sep 2006
    Messages:
    13,769
    Thanks Received:
    1,394
    Location:
    Birmingham
    Country:
    United Kingdom
    Yes, turn a negative into a positive. LOL
     
  13. Roton600

    Joined:
    9 Aug 2011
    Messages:
    49
    Thanks Received:
    3
    Location:
    Hampshire
    Country:
    United Kingdom
    What's head-lap?

    also main picture now of the broken tile not just the cracked one

    Tiles changed, but not as well as i would have liked, will upload pictures tomorrow for an opinion, as they don't sit down properly
     
  14. freddymercurystwin

    Joined:
    21 Jan 2007
    Messages:
    14,938
    Thanks Received:
    1,644
    Location:
    Devon
    Country:
    United Kingdom
    Its the distance one tile overlaps the next one down.
     
  15. Roton600

    Joined:
    9 Aug 2011
    Messages:
    49
    Thanks Received:
    3
    Location:
    Hampshire
    Country:
    United Kingdom

Share This Page