I have taken on some snagging work on a job where the original builder has since gone bump. the original Contract was to split a house into 2 flats which has been completed both flats occupied by my client and his x wife
Upstairs looks like a newish cu 8ft up on hall wall its on a tt but there is no rcd and tails look 10mm but maybe 16mm max
The downstairs has a new CU and is fitted to a new supply with earth provided so im guessing its pme it dosn't have an RCD either both flats have 4 circuits lights ring cooker heating cooker points have socket outlets.
I turned off the power to the upstairs but client has turned back on and said that its never had an RCD???
I'm going to try get upstairs flat converted to Pme as supply comes out of ground rather than from a pole. i don't think it will be a problem but then I'm a builder not a sparky.
In the meantime
I am thinking of fitting rcbos to cooker and sockets downstairs but not sure weather to fit rcbos to all circuits upstairs or just fit a 100ma rcd incomer
am I doing the best for my client or have you other suggestions
All pipework is plastic
Upstairs looks like a newish cu 8ft up on hall wall its on a tt but there is no rcd and tails look 10mm but maybe 16mm max
The downstairs has a new CU and is fitted to a new supply with earth provided so im guessing its pme it dosn't have an RCD either both flats have 4 circuits lights ring cooker heating cooker points have socket outlets.
I turned off the power to the upstairs but client has turned back on and said that its never had an RCD???
I'm going to try get upstairs flat converted to Pme as supply comes out of ground rather than from a pole. i don't think it will be a problem but then I'm a builder not a sparky.
In the meantime
I am thinking of fitting rcbos to cooker and sockets downstairs but not sure weather to fit rcbos to all circuits upstairs or just fit a 100ma rcd incomer
am I doing the best for my client or have you other suggestions
All pipework is plastic