Can I obtain a completion certificate if only part of a planning approved build was carried out?

Joined
30 Jan 2022
Messages
7
Reaction score
0
Country
United Kingdom
We obtained planning permission and Building reg approval to remove a wall between the kitchen and dining room plus building a new extension to the kitchen.
The builder called up BC who came out to inspect the Catnic once it was in position supporting the upper floor where the wall was removed .
He hasn't been called out to inspect anything else since then but photos were taken by the builder of the fireproof plasterboard used to box it in. BC haven't seen those yet.
We have now decided not to build the new kitchen extension after all due to increased costs and that the kitchen/diner was big enough for our needs.

We are now thinking of selling up and moving house.
Will we be able to obtain a completion certificate for the work that has been done so far in order to sell without complications?
Please advise.

Many thanks in advance.

Penny
 
Sponsored Links
They should be able to approve what's done, formally or informally, just explain the position and get it in writing.

Blup
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top