Hi all. I was wondering if anyone could give advice on whether the below settlement seems fair. The original builders have refused to take the job and NHBC have recommended we accept their settlement and hire builders ourselves.
This is their summary of the work that needs doing:
The works comprise replacement of cavity tray and flashing above the rear bay
flat roof abutment with the main house wall, water test bay roof to eliminate
damage to roof with an allowance included for recoating / repairing the GRP bay
roof, together with internal decorative repairs to ceiling within the bay recess
Links to images:
(Sorry, tried to attach them but it didn't work.)
They've offered just under £2,000. Unfortunately, I'm pretty clueless on how much this will cost and they're asking for a decision soon. I've asked for quotes on mybuilder, but was wondering if anyone could give an opinion on whether it seems like a fair settlement? We're in Chesterfield, near Sheffield if that makes any difference.
This is their summary of the work that needs doing:
The works comprise replacement of cavity tray and flashing above the rear bay
flat roof abutment with the main house wall, water test bay roof to eliminate
damage to roof with an allowance included for recoating / repairing the GRP bay
roof, together with internal decorative repairs to ceiling within the bay recess
Links to images:
(Sorry, tried to attach them but it didn't work.)
They've offered just under £2,000. Unfortunately, I'm pretty clueless on how much this will cost and they're asking for a decision soon. I've asked for quotes on mybuilder, but was wondering if anyone could give an opinion on whether it seems like a fair settlement? We're in Chesterfield, near Sheffield if that makes any difference.