Hello All,
looking for info on the folowing...
having the attached outside loo / utility knocked through to the main house. BC hve mad two visits and all OK, final visit due before final finish.
There was already twp sets of lights and a 2G skt in the room with another feed to the outside light and PIR. All working but clipped in etc...
My intention was to simply re-route the cables a little and bury them using the approved conduit covers, re-use the backboxes and maybe replace the fronts as one or two look bad. Other than that leave pretty much as is.
My understanding is that because this was already being used as a toilet / Utility and I am not adding anything to the system (in fact removing the 2G skt) there is no need for Part P or any official sign off?
The system will work as the old one (2 x lights) and the room will have a toilet and shower (not electric) ....not sure if I need to have a passive vent or powered extractor...if so could use the existing security / PIR supply?
all feedback welcome.
looking for info on the folowing...
having the attached outside loo / utility knocked through to the main house. BC hve mad two visits and all OK, final visit due before final finish.
There was already twp sets of lights and a 2G skt in the room with another feed to the outside light and PIR. All working but clipped in etc...
My intention was to simply re-route the cables a little and bury them using the approved conduit covers, re-use the backboxes and maybe replace the fronts as one or two look bad. Other than that leave pretty much as is.
My understanding is that because this was already being used as a toilet / Utility and I am not adding anything to the system (in fact removing the 2G skt) there is no need for Part P or any official sign off?
The system will work as the old one (2 x lights) and the room will have a toilet and shower (not electric) ....not sure if I need to have a passive vent or powered extractor...if so could use the existing security / PIR supply?
all feedback welcome.