Hey,
Been quoted £860 + VAT for this lot.
House:
To disconnect existing mains and install a new consumer unit complete with individual RCBO’s
To install a new main earth bond to water supply (7/8m cable run)
To supply and fit a replacement earth strap to the gas main
To install a 20 amp supply to shed
Shed:
To install a new consumer unit complete with individual RCBO’s
To install a twin socket above work top
To install a single socket below work top for tumble drier
To install a twin IP rated socket external
To install 2 no LED strip lights in shed
The house is 7 RCBOs, and I think he said the shed was 3 RCBOs (1 for internal sockets, 1 for internal lights, 1 for outside sockets). If TLC is anything to go by the CUs, RCBOs, SWA and T+E are approaching £500 alone.
I don't know what brand the CUs are.
Been quoted £860 + VAT for this lot.
House:
To disconnect existing mains and install a new consumer unit complete with individual RCBO’s
To install a new main earth bond to water supply (7/8m cable run)
To supply and fit a replacement earth strap to the gas main
To install a 20 amp supply to shed
Shed:
To install a new consumer unit complete with individual RCBO’s
To install a twin socket above work top
To install a single socket below work top for tumble drier
To install a twin IP rated socket external
To install 2 no LED strip lights in shed
The house is 7 RCBOs, and I think he said the shed was 3 RCBOs (1 for internal sockets, 1 for internal lights, 1 for outside sockets). If TLC is anything to go by the CUs, RCBOs, SWA and T+E are approaching £500 alone.
I don't know what brand the CUs are.