Refitting my bathroom with a new sink basin and bath. (Toilet is seperate wc and already complete)
Its a small bathroom and the sink has to come out first before the bath.. Hence the new bath will have to go in first before the sink.
Firstly i have to tile behind the sink, grout and lay floor before the new sink can go in. However this will take time for tiles to dry and will be without a sink for a day or so. Im wondering what the best process is with minumum delay and fuss..
Any advice welcome
Its a small bathroom and the sink has to come out first before the bath.. Hence the new bath will have to go in first before the sink.
Firstly i have to tile behind the sink, grout and lay floor before the new sink can go in. However this will take time for tiles to dry and will be without a sink for a day or so. Im wondering what the best process is with minumum delay and fuss..
Any advice welcome