I'm trying to find out the most popular method.
Let's say you've got a room that's going to have a shower cubicle in it. The floor is going to be tiles, but a sheet of ply is going to be fixed to the boards first. Do you:
1) Fit the tray to the floorboards than cut the ply to fit around the tray and then cut the tiles to fit?
2) Fit the ply wall to wall and sit the tray on top of the ply and cut the tiles to fit around the tray?
3) Fit the ply, then tile the entire room wall to wall, leaving just the waste clear - then fit the tray on top of the tiles?
Which do you prefer?
Which way do you see it done most often?
Let's say you've got a room that's going to have a shower cubicle in it. The floor is going to be tiles, but a sheet of ply is going to be fixed to the boards first. Do you:
1) Fit the tray to the floorboards than cut the ply to fit around the tray and then cut the tiles to fit?
2) Fit the ply wall to wall and sit the tray on top of the ply and cut the tiles to fit around the tray?
3) Fit the ply, then tile the entire room wall to wall, leaving just the waste clear - then fit the tray on top of the tiles?
Which do you prefer?
Which way do you see it done most often?