Hi all,
I've had planning permission to do hip to gable loft conversion . While the scaffolding is up, I thought I may as well have the wall ties done (it's your typical 1930's semi). Then I thought may as well have the old rendering hacked off and redone. I thought i'd combine all these tasks while the scaffolding was up and have them done all at once. So I need to do:
1. Build gable up in block.
2. Sort out wall ties.
3. Re-render.
The tradesmen team nearly ready to go on the loft conversion. Then I was worried though that hacking and heavy drilling after having a new gable built may weaken it?
So my wuestion is, do I go ahead with new gable along with hacking/rendering. Or do I leave some time between loft conversion and hacking/rendering? Or do I have the hacking/rendering done first. Any advice greatly appreciated.
Thanks.
 
Sponsored Links

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top