Hello Architexeter,
I have to apologise that I did not see the last line or so of your response sent yesterday. The only condition that is affected is the one of commencement of the development within a 5 year period.
yes, there was a very slight gradient on the existing plot and excavation was undertaken to level the plot, in some places to bed rock. Only approximately 25 ton was removed and to access the plot from the highway approximately 3m of hedgerow was removed.
Most of this excavation work was...
Hello again,
can anybody please confirm if reducing the ground levels on site constitutes commencement of the development. I am reasonably sure that the LA have now adopted a new Local Development Plan though I am not sure whether this has any bearing on this request from the LA.
If the answer...
Thanks for your quick reply and sorry I for the delay. You are right in regarding that the work had previously started but this was under the previous development that was granted and not the new application. Because of this I cannot use this as a reason that the works had started within the 5...
Hello,
my name is Allan and this is my first time here so patience please if I get something wrong. (apologies that it is also long winded).
In 2005 I helped a friend of mine attempting to obtain outline planning permission to build a small 3 bed detached house in his garden to the side of...