    New CU. Post installation questions.

    Don't know I'm afraid. I'm not going to be able to find out now until next weekend as I'm working away for the week. MCB is 50amp. Supply is PME. Thanks for you interest.
  2. C

    New CU. Post installation questions.

    Excellent replies, thanks all. A few points for him to address then. He's put the kitchen lights on the same side as the kitchen ring. He hasn't provided an installation cert yet, presumably waiting for payment. No building regs cert yet either, although I guess that can take a few days...
  3. C

    New CU. Post installation questions.

    I've had a new dual RCD CU fitted and I have a few questions about the installation. The MCBs are labelled incorrectly. Some of the neutral cables don't share the same slot number as their corresponding lives. I have a 10mm SWA running to my summer house. He's added an earth rod at that...