Hi All,
I am going to render the walls after my Extention completion.
The question is - I'm extending the backside kitchen (single floor), for the roof, do I need to fit the lead into the wall and cement it?
my roofer says just nail to the wall and render will cover that and no water will go...
Hi All,
I am doing a kitchen extension. 3m X 6m, and like to install wet ufh.
need help to decide the best way to prepare my concrete subfloor for wet ufh.
option 1: mot + sand blinding + dpm + kingspan + dpm+ concrete + ufh boards (18mm) + ufh pipes + screed + tiles
option 2: mot + sand...