Thank you for your suggestion.
The gap between two pipes are 100mm so I will filled with shingles.
Thames water specification suggests gap between foundation and pipe would be minimum 150mm if I am not wrong. Foundation can't be closer than it's requirement. Sewer pipe is 450mm below the...
I have contacted them but they are very poor to answer any question. They would ask questions over email and response in 5 working days. Over phone it is difficult to get them to get advice
Dear expert,
Any suggestions from the following response from Thames Water.
Your application was missing the following:
Sectional drawing showing proposed foundations and sewer(s)
Please confirm that the cross section provided is relevant to your build over as we cannot accept typical...