Search results

  1. S

    Metre Tails Upgrade !!!

    Does this mean that my electrician won't have to do anything apart from connecting the metre tails to the CU? Please clarify which one is done first. Thank you
  2. S

    Metre Tails Upgrade !!!

    The length of meter tails from my meter to my CU is about 4m. I have asked my electricity provider to upgrade my metre tails to 25 mm sq. What are my options in case they tell me that the length of metre tails is too much? Do I need to move my CU? Do I put a switch at the meter? Who...
  3. S

    Part P Certification

    Yes, the new 16 mm earth conductor does not fit in my old CU. Hence the new earth conductor is not yet connected until I get an ew CU. What happens to the NICEIC certification that I have now. Does it need to be updated when I get a new CU ? Who can apply for building regs certificate? My...
  4. S

    Part P Certification

    My electrcician who is a NICEIC domestic installer has put a new ring mains for my kitchen oven. However he has suggested that I upgrade my consumer unit in order to be able to connect the earth conductor. He has given me an NICEIC certificate, but it is marked as being not entirely...
  5. S

    Upgrade of meter tails and consumer unit. Please help !

    I know that it is the supplier's responsibility to upgrade the tails. However, I am told by my supplier that they do not connect the tails from the meter to my fusebox as this length is more than 3 m. They asked me to get my electrician to do this. Can I lay the wire myself in place...
  6. S

    Upgrade of meter tails and consumer unit. Please help !

    I recently re-did the electrics my kitchen and the electrician has advised me to upgrade my meter tails from 16mm sq to 25 mm sq and also upgrade the consumer unit. I am getting my kitchen wall plastered in the coming week. Since the meter tails is running inside a wall in my kitchen, i...