    suspended timber ground floor

    Thanks Jeds Currently we have 160-170 of clear gap, so I'll pull up all the bits of various building rubbish, to dig it down a little for DPM and concrete. Would need some levelling off for DPM anyway. Mike
  2. G

    suspended timber ground floor

    Ooh, quick response, thanks John! DPM straight onto the ground? The extension is 3m out from the building, 6m along it, with 3 airbricks on the single new 6m wall. Is that enough? No airbricks in the existing house due to solid concrete floors. Yep, plans show a solid concrete floor...
  3. G

    suspended timber ground floor

    Err, 6x2 joists 400mm centres, 3m span.
  4. G

    suspended timber ground floor

    Hey all, I was hoping someone could clear up some confusion on the construction of suspended timber ground floors. Does the ground surface underneath *have* to be concreted? If so, what are the depths required? My builder has put in this floor to our extension, with the correct sized...
  5. G

    New soil stack

    Thanks guys, have had building control round now, and have a much simpler plan of action set out. I can dig out and connect to the previously covered kitchen drain. Mike
  6. G

    New soil stack

    Hey all, We're almost finished getting an extension built. It extends off the side of the house, over a drain at the rear of the house, that the sink/dishwasher/washing machine waste drained into (I've already moved those), which the builder has covered. The extension is to have a bathroom...
Back
Top