We obtained planning permission and Building reg approval to remove a wall between the kitchen and dining room plus building a new extension to the kitchen.
The builder called up BC who came out to inspect the Catnic once it was in position supporting the upper floor where the wall was removed .
He hasn't been called out to inspect anything else since then but photos were taken by the builder of the fireproof plasterboard used to box it in. BC haven't seen those yet.
We have now decided not to build the new kitchen extension after all due to increased costs and that the kitchen/diner was big enough for our needs.
We are now thinking of selling up and moving house.
Will we be able to obtain a completion certificate for the work that has been done so far in order to sell without complications?
Please advise.
Many thanks in advance.
Penny
The builder called up BC who came out to inspect the Catnic once it was in position supporting the upper floor where the wall was removed .
He hasn't been called out to inspect anything else since then but photos were taken by the builder of the fireproof plasterboard used to box it in. BC haven't seen those yet.
We have now decided not to build the new kitchen extension after all due to increased costs and that the kitchen/diner was big enough for our needs.
We are now thinking of selling up and moving house.
Will we be able to obtain a completion certificate for the work that has been done so far in order to sell without complications?
Please advise.
Many thanks in advance.