I need to get power into my loft so that i can power a tv distribution amp, and to install ceiling sockets in a bedroom to supply a wall mounted tv
Unfortunatly i am unable to see any way of taking a spur from the ring main on the first floor, however i can get access to the shower supply.
The shower is fed by its own 40A fused CU, and the feed runs into a DP pullcord isolator before the shower.
My question is, is is permissable to take a spur before the DP isolator and run this through a 13A fused spur before connecting to a 2g socket in the loft? I can find nothing in the 16th ed regs that forbids this, but what do you guys think?
furthermore is it permissible to install 2 2g sockets in parallel (spur from a spur naughtyness) in this situation as in the following diagram.
if not, can i run each socket back to the 13A FCU in a (sort of ) radial configuration?
thanks for your time
nick
Unfortunatly i am unable to see any way of taking a spur from the ring main on the first floor, however i can get access to the shower supply.
The shower is fed by its own 40A fused CU, and the feed runs into a DP pullcord isolator before the shower.
My question is, is is permissable to take a spur before the DP isolator and run this through a 13A fused spur before connecting to a 2g socket in the loft? I can find nothing in the 16th ed regs that forbids this, but what do you guys think?
furthermore is it permissible to install 2 2g sockets in parallel (spur from a spur naughtyness) in this situation as in the following diagram.
if not, can i run each socket back to the 13A FCU in a (sort of ) radial configuration?
thanks for your time
nick