Yeah i think you may of miss read the post wasn't turning the joists flat, but running them from front to back instead of left to right
Like this all my joists in my house run right to left but over the extension its 11m span so i was asking if they can be run front to back over the 7.5m span
Yeah the drawings are going in i am not even near that point yet it was just something that's popped into my head as i would like to dig the small footings once i get the extension footings poured.
Yeah its ground floor, I was thinking of going solid but then my house is on timber joists and...
Building my extension and just want to know if the floor joist can be laid either way.
Reason being my extension is 11m wide by around 7.3m deep if i have the joists running left to right then i am assuming i need to put in at least two foundation trenches to support the joists if I run the...
This is where i am now
Footing are dug out just waiting for the build over agreement then can get BC to check get them poured sort out the drainage then probably call it for this year, Start again 2026
Could probably take away the patio stone and 1 day for the digger as this was more just...
After a bit of help.
So currently digging out footings for my extension. I need to move my drain which is getting a build over agreement.
My question in how do you go about putting in the new drains with out all the footings caving in I am thinking common sense just to shaw them up the dig by...