I built like your first one and Permission was rejected went to planning inspectorate appeal rejected so had to put it as per your second pic for which I would of not needed any permission as it’s permitted development. I posted a great deal on these on one of the forums hip to gable ones I think.
My lovely neighbour reported me who I asked permission from and was more then happy for me to carry out the works cause the council ain’t bothered otherwise as u can see from the pics I’ve sent u of loads like mine and more appearing. Then I got this through. So under the Nottingham City plan I...
This is the pic of how my roof was b4 hand the end terrace Putting all this to side and me agreeing to detach the dormer from the side.
Pls let me know if u think the council are right on asking me to set the tile hung dormer on the rear to be set in 300mm and to set the height down 200mm. As...
I agree with u it’s not the most pleasant looking extensions hence I’m listening to what the council r saying and going to get the brick work taken off and then it would be set in hanging with tiles and tiles going down that side. Looking like dormer. The council have allowed so many that’s...
Attached is the appeal dismissal. Think I should sue the architect who changed the first plans in order to obtain permission without my knowledge, had that been refused I would of appealed that and then when the council had asked what I intend to do I would of said I would bring it within PD.
Hi yes it was hip to gable loft conversion with rear dormer and as it was built on the wall it was not permitted as per the council who only realised when I had built this way as the rest who have built like this r all fine. Pls see docs attached and see what u think? Thanks
The council grants me full planning permission (retrospective) but say as the development would fall under PD it does not need to be assessed against local or national policy.
Then it imposes the condition to reduce the size and detach the dormer from the side wall within 6months which ended in...
I’m after some advice pls. I posted last time to say that this development is not permitted and I have to put things right. I’m planning on putting things right but covid-19 came in the way. So here it goes my architect put in for full permission and liaised with them changed the plans without...
This is not permitted development and I’ve learnt the hard way. Built like this as per the builder instructions it’s permitted development and yes he’s built hundreds like this. Then got letter from Council asking to put app in as its not permitted due to dormer not being separate and hanging...