Update, I have spoken to an escalation manager at SW, we have discussed options.
1. We dig down 150mm below the pipe, add reinforcing and pour ontop of that, sounds expensive.
2. We come back 1m, drive piles 150mm below pipe level, put a ring beam in and build ontop of that.
3. Not go any...