Hi
I have just been given a plan from a structural engineer.
I understand 99% of what we have got to do (raft with A142 mesh and R10 bars).
Can anyone explain what the following means;
1) Concrete to be C35 ready mix OR SITE MIX . . . . . "mixed using a gauge box by volume"
Is a gauge box just a way of getting the mix right - by weighing it BUT as we will be using
ready mix can I disregard the "gauge box"?
2) Slab with A142 mesh "Linted to footings with R10 bars"
Does LINTED mean join?
What has got to happen is a 1200mm raft, 225mm deep with A142 mesh 40mm from base and
A142 mesh 40mm from top, with "Z" shape R10 bars that will sink into new dining room floor
(filled with C35 - as C35 has got to be used on raft, and want to do two new floors and raft
in one hit with C35)
Just for your info - 2 days ago we had 3.5 cubic metres of C20 (20mm aggregate) as a
food fill to stabilize the ground.
Finally, is it acceptable to fill raft shuttering to 40mm with C35 and then place A142 mesh on top
of mix - then continue to fill just enough to allow second A142 mesh 40mm below - then fill to top?
Will the mix hold the mesh in place?
If not, what is acceptable plinth (cheap option if possible)?
Many thanks.
Stephen
I have just been given a plan from a structural engineer.
I understand 99% of what we have got to do (raft with A142 mesh and R10 bars).
Can anyone explain what the following means;
1) Concrete to be C35 ready mix OR SITE MIX . . . . . "mixed using a gauge box by volume"
Is a gauge box just a way of getting the mix right - by weighing it BUT as we will be using
ready mix can I disregard the "gauge box"?
2) Slab with A142 mesh "Linted to footings with R10 bars"
Does LINTED mean join?
What has got to happen is a 1200mm raft, 225mm deep with A142 mesh 40mm from base and
A142 mesh 40mm from top, with "Z" shape R10 bars that will sink into new dining room floor
(filled with C35 - as C35 has got to be used on raft, and want to do two new floors and raft
in one hit with C35)
Just for your info - 2 days ago we had 3.5 cubic metres of C20 (20mm aggregate) as a
food fill to stabilize the ground.
Finally, is it acceptable to fill raft shuttering to 40mm with C35 and then place A142 mesh on top
of mix - then continue to fill just enough to allow second A142 mesh 40mm below - then fill to top?
Will the mix hold the mesh in place?
If not, what is acceptable plinth (cheap option if possible)?
Many thanks.
Stephen