- Joined
- 24 Feb 2012
- Messages
- 66
- Reaction score
- 1
- Country
Hi all,
Bit of an issue. We specified a finished floor level with a flush bi-fold door threshold in mind, and were very clear with the builder about the required floor height. All was agreed.
Insulation was laid, concrete poured and left to set. The floor has come out approx 20-25mm lower than specified. We'll now have a 20-25mm door threshold obstruction. Should we accept this?
I was thinking it could be topped up with self leveler, but as we have underfloor heating, the slab will thicken, reducing efficiency?
The affected area is only approx 9.5sqm, so maybe £250 in self-leveling compound?
It's very frustrating as we agonsied over the floor height and took the punt on achieving flush levels!
What would you suggest? What impact on underfloor heating might an additional 25mm have on a 70mm slab?
Bit of an issue. We specified a finished floor level with a flush bi-fold door threshold in mind, and were very clear with the builder about the required floor height. All was agreed.
Insulation was laid, concrete poured and left to set. The floor has come out approx 20-25mm lower than specified. We'll now have a 20-25mm door threshold obstruction. Should we accept this?
I was thinking it could be topped up with self leveler, but as we have underfloor heating, the slab will thicken, reducing efficiency?
The affected area is only approx 9.5sqm, so maybe £250 in self-leveling compound?
It's very frustrating as we agonsied over the floor height and took the punt on achieving flush levels!
What would you suggest? What impact on underfloor heating might an additional 25mm have on a 70mm slab?