Laid 6 sq metres of floor screed 10 days ago. 3:1 grit and cement. 70mm thick over kingspan. Fairly dry mixture. Tamped down and used polyurethane float. Finished with steel trowel but did have problem getting a smooth surface.
Laid polythene sheet over and went on holiday for a week. Came back and I can't stop sweeping up loose grit/cement from the surface. Should I leave it longer before puttiong a screed levelling compound down or try something to bind the surface first?
Laid polythene sheet over and went on holiday for a week. Came back and I can't stop sweeping up loose grit/cement from the surface. Should I leave it longer before puttiong a screed levelling compound down or try something to bind the surface first?