First deadline 01/11/17
Just about ready for interim 100,000 CFS (ft³/sec) outflow. Approx' 2,800 tonnes / sec
Next year completion for theoretical capacity of 270,000 CFS


Total 2 yr cost, including emergency spillway work, approximately $500 million !

-0-
 
Sponsored Links
First deadline 01/11/17
Just about ready for interim 100,000 CFS (ft³/sec) outflow. Approx' 2,800 tonnes / sec
Next year completion for theoretical capacity of 270,000 CFS


Total 2 yr cost, including emergency spillway work, approximately $500 million !

-0-

They built that in 2 years. Im sure it would have taken us just 2yr for the lawyers and accountants to sort out the contracts.
 