1 skip £150
2t ballast £70
2t mot stone £70
14 cement (for trench concrete) £60
70 blocks £50
400 bricks £200
1t building sand (for construction and blinding) £35
5 cement (for mortar) £22
polythene membrane. £20
u/floor insulation £40
dpc and tie wires. £10
cavity insulation. £30
flooring ballast 1t £35
7cement (for floor) £17
add 20% to the above.
i would charge 2men for 4 days at 140 per day. plus profit, plus contingency.
ho hum.
2t ballast £70
2t mot stone £70
14 cement (for trench concrete) £60
70 blocks £50
400 bricks £200
1t building sand (for construction and blinding) £35
5 cement (for mortar) £22
polythene membrane. £20
u/floor insulation £40
dpc and tie wires. £10
cavity insulation. £30
flooring ballast 1t £35
7cement (for floor) £17
add 20% to the above.
i would charge 2men for 4 days at 140 per day. plus profit, plus contingency.
ho hum.