what are you all moaning about,the guy is actually connecting a 25KW boiler not a 38, at presant the pipe hes putting in will/could be(and i havent worked it all out) be ok.
If he doesnt know that the boiler is going to change to a 38 and another fire is being added its a bit early for a hanging and you guys calling him a cowboy.
Well at least someone has actually taken the trouble to read the detail I gave, thanks Lgcs.
I know from my ltd knowledge thst the feed was borderline as it stands.
At least you seem to have grasped the fact that the plumber did not see the original pipe, only the 28mm stub off the meter, the builders had ripped it out along with the tee to the existing fire, and also cut back into the final 22mm leg into the boiler.
If the builder has not involved him he has probably asumed, (ok maybe he shouldn't have), there is only the existing boiler to consider. It's all irrelevant anyway. The guy who's running the job new what had been taken out, what load was required in addition to the boiler and also of the plan to uprate the boiler when funds allow.
We did incidently contact a plumber the bricky knows, he worked out the size over the phone as we detailed it, he says the 22mm is "just" suffient, but for the boiler only.
It's what I thought and not acceptable and kevplum will not cost me any money.
Thanks again Lgcs, for recognising the idiocy of some posters on here, there never was a need to hang draw and quarter the plumber